Types of columns of industrial buildings, types of sections. Summary: Installation of reinforced concrete columns of a one-story industrial building. Requirements for quality and acceptance of works

Federal Agency for Education

Kazan State University of Architecture and Civil Engineering

Department of technology, organization and mechanization of construction

COURSE PROJECT

"DEVELOPMENT OF TECHNOLOGICAL MAP"

« Installation of reinforced concrete columns

one-story industrial building»

This may be a reflection of the earlier state of the relationship, but a growing number of successful firms may indicate the benefits of rewarding success. A progressive approach requires a more active participation of all stakeholders, rather than a “go away and figure it out” attitude. As with all aspects of life, caring relationships are contagious.

Therefore, it is important to work with people who have demonstrated that they can predict in terms of cost, time and quality. It's a familiar list of attributes, but the desire to work together is an important addition. Choosing a supply team is critical, but not always easy. Clients should select an architect and, if necessary, an engineer who is familiar with their business needs and the type of work being planned. The appointment of the main contractor and specialized subcontractors should be discussed between the client and his advisors who are already on site.

Completed: Art. gr. 11-3s

Nesterova E.R.

Checked by: Mavlyuberdinov A.R.

Kazan - 2009

1 area of ​​use.

2. Organization and technology of the construction process, works.

4. Calculation of the cost of a pile, the operating time of machines and mechanisms, wages.

5. Work schedule.

6. Material and technical resources.

Assistance is provided by reputable trade associations such as the Metal Cladding and Roofers Association and the British Construction Steelworks Association. The latter maintains a register of steel contractors indicating the type and size of contracts for which they have the skills and financial stability.

Achieving teamwork

Preferred key players should be assembled by the contractor as soon as possible. Initially, these players will be an architect, engineer, and contractors for construction and construction. As for the stages of the contract, there are two important factors. Firstly, the participants must be sure that they will do this work, although, secondly, at this stage they will not be fully provided financially. This is important because they must be free to contribute ideas to the project, safely knowing that the information will not benefit their competitors.

8. Technical and economic indicators.

9. List of used literature.

1 area of ​​use.

The technological map was developed for the installation of reinforced concrete columns of a one-story industrial building in summer time of the year.

Console columns.

Installation in a glass type of foundation using a conductor.

L = Building length - 72 meters

"technological map development"

However, joint discussions with other vendors may affect the details and costs of their work package. Obviously, there is a more cooperative approach if appropriate mechanisms are put in place, rather than advocating a fixed contract amount that may have needed to include some factors of what should be included at the detailed level. There are two possible approaches to achieve this goal.

  • Partial order to cover work in stages.
  • Letter of intent, but subject to the risk of cancellation.
Forward commitments must include the recognition that suppliers must manage the efficient use of their resources, and while they will no doubt be as cooperative as possible, it can be difficult to accommodate short-term delays in a busy schedule.

B = Building span - 18 meters

Section of columns - 0.4 m * 0.4 m;

Column length - 9.8 m;

Beam bottom mark - 8.4 m

Technical documentation for the organization of construction processes is drawn up in the form of technological maps, which are standard and compiled; for the construction of a particular object. Typical technological maps usually make up for the performance of work during construction according to standard designs and, when used, require clarification (binding) taking into account construction.

A key determinant of a successful project is the quality and timeliness of the information. In order to achieve fast and effective work, it is necessary that other major subcontractors be appointed at the same time as the structural steel subcontractor. The main contractor has an important role to play in coordinating this part of the process. All parties must agree between steel structures, roof and wall cladding, doors, glazing, moldings, etc. as part of a short introductory project, these measurements will need to be finalized in the first two weeks.

Table 1. List of volumes of technological operations

2. Organization and technology of construction process, work.

Installation of columns using a conductor .

Installation of structures begins only after a thorough instrumental check of the marks and position in terms of supports, supporting and embedded parts. The installation process has a decisive influence on the overall duration of construction and the organization of subsequent work. The installation of columns is carried out in the direction along the span of the building. With a span width of more than 18 m, the crane, moving along one of the rows of columns, installs this row of columns, mounting one or two columns from one parking lot, returns and mounts the column from one parking lot, returns and mounts the columns of another row. It is not advisable to install columns of the second row, because will delay the installation of other structures due to insufficient strength of the joints. The conductor allows you to automate the process of aligning columns and apply the forced installation of CE in the design position. The installation of columns is usually carried out by self-propelled jib and tower cranes. Columns of industrial buildings are mounted by first unfolding them at the place of installation, or directly from the vehicles by which they are fed into the area of ​​​​the installation crane. From vehicles, columns are mounted by turning on weight.

To achieve these goals, careful detailing and full coordination of contracts for steel structures and cladding is necessary. Many prime contractors address these issues by creating a strategic supply chain by choosing a small number of subcontractors in each of their core competencies. By encouraging teamwork across supply chain members, learning from one project can be captured and successfully used in the next. The entire supply chain will lead to increased efficiency of all its participants, higher quality and lower costs as the team develops.

Installation of columns .

Columns delivered to the construction site are laid out so that during installation the necessary movements and the amount of auxiliary work are minimal, so that free access is provided to the columns for inspection, attachment of equipment and slinging. The columns are laid out not flat, but in such a way that during the lifting process the bending moment from the weight of the column and equipment acts in the plane of the greatest rigidity of the column (especially this must be taken into account when installing two-branch columns).

A series of quick "design team meetings" in the critical early weeks, called and chaired by the main contractor, is in the best possible way project coordination. All major specialized subcontractors must be present, along with architects and other relevant professionals. When time is pressed, it is usually most effective for making key decisions in a meeting rather than for future meetings or follow-up development.

In early project-oriented meetings, financial commitments can be completed on the basis of information that is consistent throughout the supply chain, knowing that all relevant issues and opportunities for efficiency gains have been explored. The contract should provide a basis for resolving disagreements if things go wrong as tried and possibly fail so that problems don't arise.

Before the column is lifted, its length is measured with a steel tape measure, the distance from the lower column to the plane of the crane console or, in the absence of such, to the plane of support of the coating elements is checked. If the measured distance is less than the design one, then the bottom of the foundation glass should be “poured” with cement mortar or steel linings should be installed.

Minimizing the occurrence of problems is achieved by improving relationships between people. This is extremely difficult to achieve through the use of complex documents. People perform best when they are stimulated and want to be good, not because the paper says they should. The time spent defending the contract would be better spent improving the performance. However, protection for everyone is needed as things can go wrong.

What are they made from?

Construction is not exempt from the law of unintended consequences. If trust is to be developed, it is important to ensure that agreements reached by senior people in meetings are followed up with action in practice. Care must be taken to ensure that those working at the level of detail are fully aware of the agreements reached and understand why they will improve the efficiency of the overall project.

The installation of the column begins after the leveling layer of cement mortar in the foundation glass has gained at least 70% of the design strength.

In addition, before lifting, axial risks are applied to the four faces of the column, as well as risks of the axes crane beams.

The installation of the column is carried out by an independent flow. The crane moves along the span and sets 2 columns from one parking lot.

The most important are the actions and attitudes of people, which will be determined by the culture of the company, as well as instructions. For some time and at one time, partnership-based procurement has been lauded, this may be the situation that the industry should be aiming for.

All of these buildings have public access and egress requirements, although their populations can vary considerably in density. Unit costs are typically higher than housing costs, and this type includes buildings with the highest unit cost, such as hospitals and laboratories. Residential buildings are rather static in their function, changing only at large intervals. In contrast, most commercial, institutional and industrial buildings must respond to fairly rapid changes in their functions and a certain degree of flexibility is required in their composite systems.

The column installed in the foundation glass is centered until the marks coincide with the risks on the upper plane of the foundation glass.

To check the verticality of the columns, two theodolites are installed at right angles to the digital and alphabetic axes of the building. In this case, the cross of threads is directed at the risks applied on the glass and the lower part of the column, and then, smoothly raising the theodolite tube, at the risk at the upper end of the column.

In addition, these buildings are built by contractors who use heavy mechanized equipment not only for foundations but also for lifting heavy components. Semi-manual machines are also used, such as cement finishers, grinders, and welding generators, but most of the work is done by hand; the human hand and back remain the main tools of the construction industry, well adapted to the non-religious nature of construction.

The foundations in these buildings support significantly heavier loads than the foundations of residential buildings. Sliding supports are used, as are two types of foundations, bearings and friction. A carrier pile is a device for transferring the load of a building through a layer of soil too weak to lift the load onto a stronger layer of soil some distance from the underground; the heap acts as a column that transfers the load to the carrier layer. The length of the pile can be a maximum of about 60 meters, but is usually much less.

The leveling of the planes at the ends or consoles of the columns, on which the truss structures and crane beams are installed, is carried out according to the marking marks or along the rail suspended from the leveled plane.

The verified columns are fixed in the foundation glass with the help of conductors or steel, wooden and reinforced concrete wedges. Reinforced concrete wedges are not removed when aligning the column and sealing the joint with a concrete mixture, but are left in the concrete. Wedges are installed two at each side of the column with a width of more than 400 mm.

The piles are folded by driving them into the ground with the help of large mechanical hammers. Hollow steel pipes are also driven and the interiors are excavated and filled with concrete to form load-bearing piles; sometimes the pipe is removed when the concrete is poured. An alternative to the carrier heap is. The round hole breaks out to the bearing layer with the help of and is temporarily supported by a steel cylindrical shell. The hole is then filled with concrete poured around the rebar cage; and the steel shell may or may not remain in place, depending on the surrounding soil.

Rice. 7. Means for alignment and temporary fastening of columns in foundation glasses: a - design scheme; b - conductor diagram; c - wedge insert; g - jack mechanism

As a rule, the lower columns are installed on glass-type foundations, aligned and fixed in them, like columns. one-story buildings. And the columns of subsequent floors are already installed on the upper ends of the columns located below, or on crossbars.

The diameter of the caissons varies from one to three meters. Wood or concrete falls into soft soil where there is no heavy layer to bear under the site. The load on the structure is supported by surface friction between the pile and the soil. Floating foundations consist of flat reinforced concrete slabs or mats or reinforced concrete tubs with walls rolled around the edge of the mat to create more volume. If these buildings are not available, insulating concrete or brick walls from the freezer are placed under all external load-bearing walls to freeze from under the floor slabs.

The installation, alignment and temporary fixing of columns are practiced in the following three ways:

Installation according to risks with vertical alignment with a plumb line and welding of parts of butt joints. To ensure the verticality of the columns during alignment, if necessary, braces are used. This method is used when installing columns with platform-type joints. It can also be used when mounting columns with milled steel plates at the ends, but then temporary fastening is performed with bolts, for which corners are welded to the embedded parts in advance;

Reinforced concrete foundation walls for foundations must be carefully anchored to resist lateral earth pressures. These walls can be built in excavations, cast in wooden moulds. Sometimes a wall is created by interlocking a steel sheet laid into the ground, excavating on the side of the basement, and pouring a concrete wall against it. Deeper foundation walls can also be built using the wall slurry method, in which a linear series of closely spaced coffered holes are drilled in succession, filled with concrete, and allowed to harden; the gaps between them are dug out with special ladles, and also filled with concrete.

Installation of columns on the heads of the columns, on which single conductors are pre-fixed with screws (the heads of the lower columns are usually 0.5-0.8 m above the floor level). The column installed in the conductor is fixed with adjusting screws and aligned along the center axes and vertically. Apply various designs single conductors;

During excavation and drilling operations, the holes are filled with a high-density liquid, which holds the excavation from collapse, but still allows the excavated material to be retrieved. Finally, the cellar is dug, adjacent to the wall, and the wall is pressed against the pressure of the earth.

The structures of these buildings are mostly skeletons various types, due to the large spaces their users demand and the need for further flexibility. Wood is used, but on a much reduced scale compared to residential buildings, and above all in regions where wood is readily available. The public nature of commercial and institutional buildings and the hazards of industrial buildings generally require them to be non-combustible and this largely precludes the use of lightweight timber frames.

Installation of columns on the heads of the lower columns with temporary fixing and alignment with the help of group conductors for four columns. The group conductor is installed and fastened with clamps to the heads of the columns installed below. Each of the four columns is installed, fixed and aligned in the same way as installations with single conductors. Flooring with railings at the top of the conductor allows you to mount floor structures. After the installation work is completed and the elements are fixed in one cell of the building, the conductor is moved to the next cell. The conductors are lifted to the next floor by a crane.

The most common group conductor is a frame-hinged indicator (RSHI). RSHI is a device consisting of spatial lattice scaffolds, on which there is a hinged (floating) frame with corner stops for fastening four columns at once in the upper position, retractable and rotary cradles for assemblers and welders. At the corners of the frame for temporary fastening of columns in the design position, angular faceted clamps (stops) are installed - two swivel and two folding, which can occupy a transport or working position and do not interfere with the installation of crossbars and plates.

With the help of such a conductor, the columns are mounted without additional alignment. They are lifted one by one, brought by a crane to the corresponding clamps of the conductor and smoothly lowered onto the heads of the underlying columns. The side edges of the bottom of the mounted column are fixed with a tensioning device of the lower latch fixed to the column head, pulling it close to the sides of the latch. In this way, their exact alignment with the corresponding faces of the column head is ensured. The top of the column is fixed with an upper grip - indicator frame lock, bringing the column to a strictly vertical position.

Sealing joints and reinforced concrete structures:

Monolithic joints and seams with a mortar or concrete mixture are carried out after verifying the correct installation of structural elements, acceptance of welded joints and anti-corrosion protection of steel embedded parts and reinforcing bars. Concrete or mortar mixture is fed into the joint under pressure or in a free-mechanized way or manually. The process of filling joints and seams with mortar and concrete mixture consists of supplying and laying mortar or concrete mixture into the seams, followed by compaction.

Work organization of workers:

The organization of labor of workers in construction includes the appropriate placement of people in the production process, the division into labor cooperation, methods of rationing and stimulating labor, the organization of jobs, their maintenance and the necessary conditions labor. The scientific organization of labor requires constant improvement of labor processes on the basis of the latest achievements of science and practice, aimed at a steady increase in labor productivity, improvement of conditions and improvement of work culture, and the transformation of labor into a vital need.

The scientific organization of labor is created on the basis of a complex of technical, organizational and economic measures that ensure the most rational division and cooperation of labor, improvement labor processes and organization of jobs.

Methods of organizing labor can be different depending on the structures used, methods of work, machines, installations and other means of production.

To perform various operations in the construction process, workers are grouped into units, depending on the nature of the operations that need to be performed by the unit or team. The links usually consist of two or three workers of the same profession, but with different qualifications.

Several links performing the same construction process are combined into a team headed by a foreman.

Brigades are specialized and complex. The composition of a specialized team includes workers of the same specialty, up to 25 people. Complex brigades unite workers of different professions to perform a specific set of works, part or whole structure. The complex team includes approximately 50 workers.

A team of final products is organized for the erection of individual structural elements (foundations, walls, ceilings, etc.) or the building (structure) as a whole.

Every year the number of teams of workers performing work by the method of team contracting on the basis of cost accounting increases. Both the brigades of the general contracting organization and the subcontracting organization are transferred to the brigade contract. The transfer of teams to economic accounting should be preceded by the development of work schedules, the supply of basic materials, structures, products to the facility, the compilation of labor costs and wages, and the determination of the cost of work assigned to the team.

One of important indicators The activity of construction workers is labor productivity, i.e., the amount of working time spent per unit of output, defined in man-hours or man-days. The lower the cost of labor in man-hours per unit of output, for example, per 1 m3 of brickwork, per 1 m2 of plastered surface, etc., the higher labor productivity.

Construction processes at the construction site or part of the facility are carried out in a certain order (combining in time), ensuring the rhythm of production and the most rational use of labor and technical means. The object is divided into areas, i.e. areas where there is a sufficient amount of work to complete the construction process by the team for a certain time (usually at least one shift). The number of grips should be sufficient so that teams of different professions can perform construction processes at the same time, moving from one grip to another after finishing work. For some processes, the grip is divided by height into tiers, for example, when brickwork, which cannot be immediately completed to the height of the floor and which requires the construction of a scaffold, The part of the grip allocated for work by one link of workers is called a plot.

The space in which the workers involved in the production are located, as well as the machines, materials and parts necessary for the construction process are located and moved, is called the workplace. The area allotted for the work of a brigade or link for a certain period is called the front of work. The size of the scope of work determines the size of the team involved in the construction process. The scope of work is measured in units of length, area or volume. For the correct organization of complex construction processes at the facility, technical documentation is developed, which determines the nature of the process and its composition, production methods and means of mechanization of works, calendar schedule of production, required amount workers by profession and their qualifications, materials, parts, tools and organization of the workplace.

Sometimes the construction object is conditionally divided vertically into technological tiers. The need for such a division arises when design features object, the front of work opens in the process of their execution. For example, when concreting columns by lowering the concrete mixture from above, while the height of the tier according to SNiP should not exceed 5 m in order to avoid delamination of the concrete mixture during its fall.

Table 2. Qualification composition of a brigade or link

link number Running processes Qualification composition of workers Number of workers
1 Installation of columns in the foundation glass Structural assembler of the 5th category 1
1
Structural installer 3rd category 2
Structural installer 2nd category 1
Crane operator 6th category 1
2 Sealing joints Structural installer 4 category 1

Structural installer 3

1

Rice. 1.1 Scheme of unloading and preliminary layout of columns in buildings with a span of 12, 18, 24 m.

1 - Foundation glass; 2 - column; 3 - vehicle; 4 - crane; 5 - traverse.


Rice. 1.2. Scheme of installation of columns in buildings with a span of 12, 18, 24 m:

1 - foundation glass; 2 - column; 3 - vehicle; 4 - crane; 5 - traverse.

Alignment and temporary fixing of columns is carried out with inventory wedge inserts or conductors. Moreover, for columns weighing 8 tons, the conductor is installed on the foundation and fixed on the column after it is installed in the foundation glass. For heavier columns, conductors are installed, aligned and fixed on the foundation before the installation of the column.

After installing a number of columns, their design position is finally verified and the joints of the columns with the foundations are sealed. Columns for embedding are rented out in batches.

Scheme of installation of one-story industrial buildings :


The columns are delivered to the construction site by road, while light columns (weighing up to 8 tons) are mounted with preliminary layout at the installation sites in the area of ​​​​the assembly crane, and heavy ones are delivered to the assembly crane according to an hourly schedule and mounted directly from vehicles.


Rice. 1.3. Schemes of crane movement when installing columns in spans of 12, 18, 24 m.


Rice. 1.4. Scheme of unloading and layout of crane beams with a span of 6 and 12 m:

1 - column of the extreme row; 2 - crane beam; 3 - bulk carrier; 4 - wooden lining; 5 - column of the middle row; 6 - truck crane; 7 - brace on a hemp rope; 8 - sling.

Depending on the span (12; 18; 24m or more) and the pitch of the columns (6; 12m), various schemes erection of columns and movement assembly cranes(Fig. 1.2, 1.3, 1.4).

It is advisable to mount crane beams in an independent flow directly from vehicles. The installation of beams in the design position is carried out according to axial risks on the beams and consoles of the columns. The beams are temporarily fixed to the supports with anchor bolts. The final alignment of the crane beams is carried out within the mounting grip or temperature section, using geodetic tools, after which all fasteners of the beams and embedded parts of the columns are checked.

Methods for laying out columns before installation: a - light; b - heavy;


For the installation of light columns of one-story buildings with jib cranes, a fork head, made in the form of a cantilever attachment to the head of the boom, which has blocks for reeving ropes, can be used. The headband is equipped with a device for semi-automatic slinging. It allows the use of cranes with a shorter boom length and, therefore, better use of their lifting capacity. In addition, the minimum suspension length reduces the swing of the column and allows their carrying capacity. In addition, the minimum hanger length reduces column sway and improves installation accuracy.

If necessary, the bottom of the glass is leveled with a layer of cement mortar. The columns are installed in the foundation glasses after the strength of this solution reaches at least 70% of the design. Alignment and temporary fixing of columns, depending on their size, weight and installation location, is carried out using individual conductors of inventory steel, wooden, reinforced concrete wedges (two at each side of the column).

The column installed in the foundation glass is centered until the marks coincide with the marks on the upper plane of the foundation.

To check the verticality of the column, two theodolites are placed at right angles to the digital and alphabetic axes of the buildings. In this case, the visual axis of the theodolite is combined with the risks marked on the glass in the lower part of the column, and then, smoothly raising the theodolite tube, with the risk at the upper end of the column. The distance outside the theodolite from the column being verified is taken such that at the maximum rise of the pipe, its angle of inclination does not exceed 30-35 '.

The planes at the ends or consoles of the columns are leveled according to marked marks or along a rail suspended from the leveled plane.

The verified columns are fixed in the foundation glass with the help of conductors.

Warehouse design

Warehousing of prefabricated structures is carried out in stacks or cassettes, in which structures working in a vertical position are placed - Wall panels, farms, etc.

The aisles between the stacks are arranged with a width of 0.4 to 1 m and are arranged through 2 stacks in the longitudinal direction.

Aisles with a width of 3 ... .4 m for the movement of vehicles and handling mechanisms are arranged at least every 100 m.

The width of the warehouses is taken from the calculation that all elements rise from the warehouse without additional re-edging and movement, i.e. they must be within the range of service cranes.

In the warehouse, prefabricated elements are placed in the same position as on vehicles during transportation. Horizontally stacked structures are laid on wooden linings, the distance between which is linked to the operating conditions of this structure.

The layout of elements in the warehouse can be separate, in which all elements of the same type are stored together, and group, when the layout and installation of elements of different types is provided from one parking of the assembly crane.

Construction site roads

Construction roads include access roads that connect the construction site to the general road network, and internal construction roads that transport goods within the site. Access roads, as a rule, are made permanent, and internal roads before the construction of the main facilities.

Roads at construction sites can be dead-end and roundabouts. At the end of dead ends there should be turnarounds, and in the middle part, if necessary, sidings. Based on the standard size of the car (rectangle 2.5 m wide and 3.8 m high), the width of the carriageway of the road with a single lane is 6 m. not less than 6 m.

When using heavy machines, the carrying capacity of 25 ... 30 tons or more, the width of the roadway increases to 8 m. If large and long loads are delivered to the construction site, the width of the road can be further increased.

The radius of curvature of roads is dictated by the ability to maneuver individual vehicles and road trains, i.e. their turning ability when moving forward without using reverse gear. Usually, the minimum radius of curvature is taken as 15 m, in this place the width of the carriageway is increased - with a road width of 3.5 m at the rounding, it will be 5 m.

Structurally car roads consist of subgrade and pavement. To drain surface water, the road is given a double slope on straight sections of the track, and a single slope on curved sections.

The pavement consists of several layers - the underlying sandy layer, the bearing base (crushed stone, concrete, reinforced concrete) and the coating. To reduce the costs for the construction period at the construction site, it is advisable to build future permanent roads without top coating. Only the lower layers of the road are suitable, it is even more efficient to lay a temporary coating of reinforced concrete road slabs on a sandy base. The main coating in this case should be carried out before putting the facility into operation.

As reinforced concrete road slabs, rectangular and wedge-shaped slabs are used. Rectangular road slabs (2.5 ... 3.0 m long, 1.0 ... 1.5 m wide, 0.14 ... 0.22 m thick and weighing 0.63 ... 1.8 tons) are easy to manufacture and working with them on the construction site, they can withstand increased loads, they are suitable for use immediately after their laying at any time of the year and in any weather. Roads are more often arranged with track - one - and double-track with sidings. Wedge-shaped slabs make it possible to cover the roadway immediately for the entire width of the road, the radius of curvature on turns can be any. On straight sections, the plates alternate, placing them either with a wide or a narrow side. For such slabs, there is no need for the construction of individual sections of the road (especially on bends) in a monolithic design.

The cost of building, repairing and maintaining such roads under conditions of typical traffic intensity for construction sites usually pays off in 1.5 ... 2 years. Prefabricated - collapsible slabs are the property of the construction organization and require their repeated use.

Loading and unloading construction materials

Transportation of building materials to the facility is associated with the need to load them at the place of departure and unload at the place of arrival. These operations are almost completely mechanized; general construction and special machines are used to perform them, or they are part of the design of vehicles.

The first group includes special assembly cranes, cyclic and continuous loaders, mobile belt conveyors, mechanical shovels, pneumatic unloaders, etc. The second group includes dump trucks, vehicles with self-unloading platforms and autonomous unloading facilities, etc.

In construction, the transportation of small-piece materials and products using packages and containers is used. A package is a consignment of cargo laid on a special pallet. Packages must be formed in such a way that their shape is preserved at all stages of the movement.

A container is an inventory reusable device or container. The universal container is designed for transportation of various categories of cargo; it is closed, equipped with devices for loading and unloading. Special containers are designed to transport a certain type of cargo - roll materials, finishing tiles, linoleum, electrical fittings per building section, etc.

Warehousing of material elements

The material elements delivered to the construction site are stored in on-site warehouses intended for their temporary storage - the creation of a production stock.

There are two main types of production stock - current and insurance. The current stock constitutes the material resource between two adjacent deliveries. Ideally, the current stock should be sufficient to ensure the continuous production of work. However, taking into account possible disruptions in the supply of materials and structures, they create an insurance stock, which should smooth out, compensate for the uneven replenishment of the current stock. The minimum stock of prefabricated structures in the warehouse is usually taken for 5 days of work.

The level of production stock depends on the accepted organization of work - installation "from wheels" or from a warehouse, the remoteness of the object from the central supply bases, the type of transport and other factors. The presence of a warehouse with an excessive stock of structures or materials, on the one hand, ensures uninterrupted production of work, and on the other hand, leads to a "freeze" of investments in this construction, i.e. to its rise in price. Therefore, the general contractor is obliged to find the optimal volumes of on-site warehouses. On-site warehouses are arranged as closed, semi-closed and open.

Closed warehouses are used to store expensive or spoiling materials in the open air - cement, lime, gypsum, plywood, nails, etc. They can be aboveground and underground, one-story and multi-story, heated and unheated.

Sheds - semi-closed warehouses are erected for materials that do not change their properties from changes in temperature and humidity, but require protection from direct exposure to the sun and precipitation - wood products, asbestos cement, roofing felt, and other enclosing and finishing materials.

Open warehouses are designed for storage of materials that do not require protection from atmospheric influences - bricks, concrete and reinforced concrete elements, ceramic pipes, etc. Warehouses, as a rule, are located in the area of ​​​​the assembly crane serving the facility. This allows it to be used for unloading incoming goods, mainly in free time or in shifts free from installation. During installation, it is advisable to use lighter self-propelled cranes for unloading operations.

Part of the open warehouse, including the site for pre-assembly of structures, can be serviced by special cranes - self-propelled on caterpillar and pneumatic tracks, gantry, tower cranes - loaders. These mechanisms are used for loading enlarged structures onto vehicles for their subsequent delivery to the places of laying or installation. Typically, in a warehouse, heavy loads are placed closer to the cranes, and light loads further away, as they can be lifted at a longer reach of the crane.

Storage areas should be flat, with a slight slope within 2 ... 5% for the flow of storm and melt water. On poorly draining soils, it is recommended, in addition to planning, to carry out a small addition of crushed stone or sand - 5 ... 10 cm. If necessary, carry out surface compaction. Sections of the storage area, where materials (mortar, sand, etc.) are unloaded directly from vehicles, should be made in the same constructive solution as the adjacent access roads.

For different designs and prefabricated products, they allocate their own storage areas. They are separated from one another by through passages with a width of at least 1 m. Different materials have their own storage rules.

Brick is stored according to grades, brands, color of the front surface. Brick delivered in bulk is stacked with dressing and up to 1.6 m high, while the brick with non-through voids is down. Bricks in packages or on pallets can be stacked in a warehouse in one or two tiers.

Precast concrete is placed on inventory linings and gaskets, the laying places of which must correspond to the risks on the prefabricated elements. When storing elements in a stack, the spacers between them are stacked one above the other strictly vertically. The cross section of gaskets and linings is usually square, with a side of 6 ... 8 cm. The dimensions are selected so that the overlying elements do not rest on the mounting loops or protruding parts of the underlying elements.

Before installing columns:

Concrete or install foundations for columns and check their compliance with the design position using geodetic instruments;

filling up the sinuses of the foundations;

· apply the risks of the installation axes on the upper face of the foundations and the side faces of the columns;

close the glasses of the foundations with shields to protect them from pollution;

arrange roads for the passage of a crane and cars;

· to prepare platforms for warehousing of columns at the place of their installation;

· Deliver the necessary installation tools, fixtures and tools to the installation area.

Reinforced concrete columns at the facility are laid out on wooden linings in the area of ​​​​the erection crane. The thickness of the pads must be at least 25 mm.

In the absence of mounting loops, the columns are slinged with a noose loop in the places indicated at the factory. The rope must not have knots or twists. To protect the rope from kinks and rubbing, steel linings should be placed under the ribs of the columns.

Each column must be inspected so that it does not have deformations, damage, cracks, shells, chips, exposed reinforcement, concrete sagging; check the geometric dimensions of the column, the presence of a mounting hole, the correct installation of steel embedded parts.

For alignment and temporary fixing of columns, a set of mounting equipment is used, placed in a container. The kit includes inventory wedge inserts and other devices (RF-595 TsNIIOMTP).

Artists:

· Worker performing installation work, senior in the link;

Worker performing installation work;

· Worker performing rigging work.

Work production technology

Preparing the column for installation (Fig. 13), the performer is a worker performing rigging work

Preparing the column for installation .

Rigger

1. Checks column markings.

2. Cleans the ends of the column from the influx of concrete and dirt with a metal brush.

3. Using a metal meter, divides one plane in width into two equal parts in two places (at the level of the top of the foundation and at the top of the column) and draws axial risks with a pencil.

4. Using similar techniques, he inflicts risks on the second plane perpendicular to the first.

5. Gives a signal to the crane operator to apply the universal gripper 3 to column 2.

6. Puts on the grip from the upper end of the column and, using the inventory handle, tightens the nuts of the clamping device.

7. Departs at a distance of 7 ... 8 m from the column.

8. Gives a signal to the crane driver to raise the column to a height of 200-300 mm.

9. Inspects fasteners.

10. Gives a signal to the crane operator to move the structure to the installation area

Preparing the installation site

Installers 1st, 2nd

1. The 2nd installer lays out the tool, fixtures, inventory.

2. Then he checks the cleanliness of the foundation glass.

3. After checking the risks on the upper plane of the foundation glass.

4. The 1st and 2nd installers lay out the tools and fixtures according to the scheme for organizing the workplace.

5. The 1st installer installs and aligns two theodolites.

Reception, installation and fixing of the column

Column alignment with a single jig

Installers 1st, 2nd

Rice. 16. Scheme of alignment of the column with jacks:

1 - worker performing installation work, senior in the link, 2 - column, 3 - worker performing installation work, 4 - jack, 5 - foundation

Installers install two jacks 4 on opposite sides of the column and rest their screws against the plane of the structure

2. The 1st installer checks the coincidence of the axial marks on the column and foundation sleeve 5 and gives a signal to move the bottom of the column in the desired direction.

3. The 2nd installer tightens the jack screw, which displaces the column, and loosens the screw at the second jack.

4. Having obtained a combination of marks, the installers rearrange the jacks to another axis of the column and, with similar movements, align the element relative to the second axis.

5. Installers take one conductor truss and install it on the foundation glass on both sides of the column.

6. Installers tighten the coupling bolts, connecting trusses.

7. The 1st installer gives a signal to the crane operator to loosen the slings.

Installers unstrapping the column (see below).

9. The 1st installer guides the pipe axis of the first theodolite at risk at the bottom of the column and fixes the horizontal circle.

10. Then he moves the theodolite tube to the risk at the top of the column.

11. If there are deviations, the 1st installer gives a signal to the 2nd installer to move the top of the column.

12. The 2nd installer, by turning the screw of the corresponding support of the conductor, moves the top of the column in the desired direction.

13. Similarly, reconciliation is carried out in the other direction.

Column bridging

Installers 1st, 2nd

Rice. 17. Column bridging scheme:

Column, 2 - clamping device ties, 3 - worker performing installation work

1. The 1st installer gives a signal to the crane operator to loosen the slings.

2. The 2nd installer, using the inventory handle, unscrews the nuts of the two threaded ties of the clamping device 2.

3. The 1st installer removes the ties from the slats and gives the signal to the crane operator to raise the grapple.

3. Requirements for the quality and acceptance of work.

Before starting work on the installation of columns, the following organizational and preparatory measures must be completed:

Structures must pass incoming quality control and comply with the requirements of design and regulatory documentation;

The foundations for the columns were erected;

Preparation and layout of the installation site with backfilling of the sinuses of the foundations;

Mounting axes (risks) are applied to the glasses of foundations”;

The "Act of Intermediate Acceptance of Foundations" was issued.

The installation of columns should be carried out only after the acceptance of foundations and other supporting elements, including a geodetic check of the compliance of the planned and high-altitude position with the design one.

Operational quality control of the installation of columns .

Operational quality control

Name of operations subject to control Subject of control Technical requirements for the quality of operations Methods and means of control Control time Attracted controlled services
Preparation of structures for installation Appearance of structures Absence of structural defects, their integrity, compliance of structures with the requirements of the project Visually Before the start of work
Compliance of construction marks with the project Marking of structures must correspond to the project
Correct application of installation marks Mounting axes fixing the centers of the sides must be applied with oil paint on the structures to be mounted.
Preparation of the site for the installation of columns Cleanliness of the surface of the base for the installation of structures The surface of the base for the installation of columns must be cleaned of dirt and water, metal parts must be degreased, cleaned of corrosion, mortar
Availability of an executive scheme for the installation of foundations Installation of columns should be carried out only if there is an executive diagram for the installation of foundations, indicating the mounting marks of the made gravy
Installation of columns Compliance with the technological sequence of installation of columns The technological sequence of work must comply with the requirements specified in the technological map According to the technological map

Columns must be installed by combining the risks indicating the geometric axes in the lower section of the mounted structure with the drawings:

Split axes when installing columns in foundation glasses;

Geometric axes of lower installation structures;

In all other cases.

surveyor
Installation of columns Correspondence of the installation of columns with installation risks If there are embedded fixing devices, the installation of columns should be carried out using these devices. The displacement of the axes of the columns in the lower section relative to the center axes (marks) should be no more than 5 mm Instrumental: theodolite, metal meter During the production process Surveyor
Installation verticality

The deviation of the axes of the columns in the upper section relative to the center axes should be at the height of the columns, m:

Up to 8…….20mm;

From 8 to 16….25mm;

From 16 to 25….32 mm;

From 25 to 40….40mm;

Correspondence of the marks of the top of the columns with the design ones The deviation of the marks of the tops of the columns or their supporting platforms of one-story buildings from the design ones should be no more than 10 mm. A variety of marks for the tops of columns or their supporting platforms of each tier or floor within the area being verified, mm: with contact installation (where n is the serial number of the tier) 12 + 2 n Instrumental: tape measure, metal meter
Monolithic mounting nodes The quality of monolithic columns in the glasses of foundations The fixing of the columns in the design position should be carried out by embedding the joint of the columns with the glasses of the foundation with a concrete mixture on fine gravel or crushed stone with a brand corresponding to the brand of concrete or project laboratory After erection of structures laboratory
The quality of the monolithic joints of the mounted columns When embedding the joints of mounted columns with previously installed ones, the joints of the columns must be sealed by injecting the finished concrete mixture of the design grade onto the joint of the formwork According to the technological map After the installation of the structure

Laboratory

Actual position of mounted columns After the complete elimination of unacceptable deviations and the final fixing of the structures, a geodetic survey of the actual position of the structures should be performed with the drawing up of an executive diagram of the floor of a building or structure Upon completion of work Engineer surveyor

6. Material and technical resources

Table 6. The need for basic materials, semi-finished products and structures

Table 7. Need for machines, equipment, tools and fixtures

Name Brand Qty Specifications
1 2 3 4
Tap MKG-25BR 1
Conductor
TARA
Hopper for concrete, V = 1 m3 GOST 21807 - 76 3
Solution bucket, V = 0.3 m3 4
Water tank, V = 1 m3 1
Warehouse - tool container 1
SAFETY MEANS
Construction site fencing
signal fence
Crane rail guard post
Safety device for fitters 1
Mobile searchlight mast 1
Workplace lighting fixture 2
Construction helmet GOST 12.4.087.84 5 - 7
Fuse Belt 5 – 7
Technical rubber gloves 2
Signal flag 2
Goggles 2
MEASURING TOOL
Theodolite T-15 or T-30 in combination with a tripod ShR-40
Level NT for leveling the horizon complete with a tripod SHT - 120
Leveling rail 2

Roulette metal P3 - 20,

Folding metal meter MSM-74
Construction level USZ-500 GOST 9416-83

Construction steel plumb line OT-400

GOST 7948-80

Steel square GOST 3749-77 2
Roulette GOST 7502-98 2
Marking cord in the case 1
Rail with level 4
Set of crayons for marking axles 1
Scriber OTD-967/2 2
Assembly spanners for bolts 18-27 mm 2
Assembly wrenches for bolts 18-27 mm 1
Single-sided wrenches (colic) for 18-27 mm bolts 1
One-sided wrenches for 27mm bolts
Construction scrap LL-28A 4
Scrap assembly LM-24 (LM-32) 4
Construction shovel 4
Mortar shovel LR 4
Kelma KB GOST 9533-81 4
Steel scraper SS 4
Wire brush 2
Sledgehammer sharp-nosed, weighing 3 kg GOST 11402-75 2
Sledgehammer sharp-nosed, weighing 5 kg GOST 11401-75 2
Locksmith's hammer, weighing 800 g GOST 11042-90 2
Chisel 2
Bucket galvanized 2
Hemp ropes, 12 mm in diameter, 30 m long 2

7. Measures for labor protection and safe work.

When performing work, be guided by the "Safety in Construction".

When erecting buildings and structures, it is prohibited to carry out work related to the presence of people in one section (capture, area) on floors (tiers) above which the movement, installation and temporary fixing of elements, prefabricated structures or equipment is carried out. When erecting one-story buildings or structures, the simultaneous execution of installation and other construction works on different floors (tiers) is allowed if there are reliable between them (justified by the appropriate calculation for the effect of shock loads) interfloor ceilings by written order of the chief engineer after the implementation of measures to ensure the safe performance of work, and subject to the presence of specially appointed persons responsible directly at the place of work for the safe production of installation and movement of goods by cranes, as well as for monitoring the implementation by the crane operator, slinger and signalman of production instructions for labor protection.

Slinging methods for structural elements and equipment should ensure their supply to the installation site in a position close to the design one.

It is forbidden to lift prefabricated reinforced concrete structures that do not have mounting loops or coils that ensure their correct slinging and installation.

Cleaning of the structural elements to be installed from dirt and ice should be carried out before they are lifted.

Slinging of structures and equipment should be carried out with load-handling devices that meet the requirements and provide the possibility of remote slinging from the working horizon in cases where the height to the load-handling device lock exceeds 2 m.

During breaks in work, it is not allowed to leave the raised elements of structures and equipment on weight.

For the transition of installers from one structure to another, inventory ladders, walkways and ladders with railings should be used. Installers are not allowed to cross established structures and their elements (trusses, crossbars, etc.), on which it is impossible to install a fence that ensures the width of the passage without the use of special safety devices (a rope securely stretched along the truss or crossbar to secure the safety belt carabiner, etc.)

It is not allowed to carry out installation work at a height in open places with a wind speed of 15 m / s or more, with sleet, thunder or fog that excludes visibility within the work. Work on the movement and installation of vertical panels and similar structures with a large sail area should be stopped at a wind speed of 10 m/s or more.

It is not allowed to find people under the mounted elements of structures and equipment until they are installed in the design position and secured. If it is necessary to find workers under the mounted equipment (structures), as well as on the equipment (structures), special measures must be taken to ensure the safety of workers.

On the site (grip) where installation work is being carried out, other work and the presence of persons are not allowed.

8. Technical and economic indicators per unit of work


10. List of used literature.

1. ENiR, collection 1. Intra-construction transport works. Moscow. Price list, 1987, 40s.

2. ENiR, collection 4. Issue. 1. Installation of prefabricated and installation of monolithic reinforced concrete structures. Buildings and industrial structures. Moscow, Stroyizdat, 1987, 64p.

Lecture 4, 5

4.1. Types of columns and their scope.

4.2. Fundamentals of design and calculation of solid columns.

4.3. Fundamentals of design and calculation of through columns.

4.1. Types of columns and their scope.

Prefabricated reinforced concrete columns of one-story industrial buildings by appointment can be divided into:

1. columns for buildings without cranes;

2. columns for buildings equipped with overhead or other cranes that require crane runways supported by columns (columns for buildings with electric overhead cranes of mass use, columns for buildings with manual overhead cranes, etc.).

By location in the building the columns are divided into

Columns of extreme rows (they are also used in rows adjacent to longitudinal expansion joints);

Columns of the middle rows, usually having an average vertical axis of symmetry.

Wall railings adjoin the extreme columns from the outside.

The extreme columns are divided into:

Basic (perceiving loads from hinged panels, cranes, coating structures);

Half-timbered (serving for fastening walls);

Tie columns (connected by steel vertical ties to absorb horizontal forces).

Half-timbered columns are installed at the ends of the building and between the main columns at the longitudinal walls with a step of the main columns of 12 m and 6-meter wall panels.

By design columns are

Constant and variable section in height (stepped columns);

Solid (rectangular or I-section);

Through (two-branched), which can be diagonal and diagonal (diagonal columns are used for power plants up to H= 50 m);

Hollow (rectangular and round section).

By type of material:

From heavy concrete (more than B 20);

From lightweight concrete (used less often, mainly in areas where there is little fine aggregate, for example, the Far East).

Reinforcement method:

No prestressing;

With prestressing (for flexible long elements from transport conditions).

For buildings without overhead cranes, mainly solid columns of rectangular section with dimensions of 300 × 300 ÷ 400 × 800 mm are used (Fig. 4.1).

I-section columns (Fig. 4.2) are more economical than a rectangular section, but more laborious to manufacture.

Ring columns made of centrifuged concrete (Fig. 4.3) reduce the consumption of steel and concrete up to 30%. This is due to the rational shape of the cross section of the columns and an increase in the strength of concrete by an average of 1.5 times due to the compaction of the concrete mixture by centrifugal forces. The centrifugation method makes it possible to mechanize and automate the technological process of manufacturing columns, which is an additional advantage of such products.



Rice. 4.1. Columns for buildings without overhead cranes

Rice. 4.2. I-section columns

Rice. 4.3. Ring section columns

Columns of channel section (U-shaped section) also make it possible to use the properties of high-strength concrete and reinforcement to the fullest extent (Fig. 4.4). Experiments show that the use of high-strength concretes in combination with non-stressed high-strength reinforcement leads to savings in concrete and steel up to 30%.

Rice. 4.4. Channel section columns

For buildings with overhead cranes, solid and two-branch (through) columns with consoles are used (Fig. 4.5). The dimensions of the cross-section of the columns in the over-crane part are assigned from the condition of the location of the crane equipment.


Rice. 4.5. Columns for one-story buildings with overhead cranes

a - solid rectangular section; b - through two-branch

For solid columns, the section height is: for the extreme ones - 380, 500 mm; for medium - 600 mm. For the crane part of solid columns, the section height increases to 600 and 800 mm, respectively. The column section width is 400 and 500 mm (larger dimensions correspond to a column spacing of 12 m).

Crane part of two-branched columns consists of two uprights-branches interconnected by transverse struts. The distance between the axes of the struts is taken s = (8¸10)×h, Where h\u003d 250 or 300 mm - the height of the section of the branch. For medium columns, the height of the entire section h1= 1400¸ 2400 mm, for end columns - h1= 1000 ¸ 1900 mm. Column section width b = (1/25¸1/30)×H. The cross section of the over-crane part of the columns is rectangular in size 500 × 600 mm.

The spacers are placed so that the size from the floor level to the bottom of the first above-ground spacer is at least 1.8 m and provides a convenient passage between the branches (Fig. 4.5, b).

The connection of a two-branch column with the foundation is carried out in one common glass (Fig. 4.6, a) or in two separate glasses (Fig. 4.6, b), which reduces the volume of concrete laid during installation.


Rice. 4.6. Structures for connecting a two-branch column with a foundation

a - with one common glass; b - with two separate glasses; c - when installing dowels; 1 - concrete embedding; 2 - column

The depth of the embedding of the column in the foundation glass is taken equal to the larger of the two dimensions:

or

In addition, the depth of the embedment of the column must be checked from the conditions of sufficient anchoring of the longitudinal working reinforcement.

If a tensile force occurs in one of the branches of the column, the connection of the column with the concrete of the monolithing is carried out on dowels (Fig. 4.6, c).

Centrifuged columns with consoles are made prefabricated-monolithic. They consist of an upper and lower (or two lower) trunks, interconnected by a console made of monolithic concrete classes B 25 ÷ B 40.

Columns of all types are reinforced with welded frames, the longitudinal rods of which are made of steel of class A-III (A400) with a diameter of at least 16 mm, and the transverse ones are made of steel of classes A-I (A240) and Bp-I (Bp 500). When using high-strength concretes of classes B 45 ÷ B 60, it is advisable to reinforce the columns with non-stressed reinforcement of class A-IV (A600). This allows to reduce metal consumption by 20 ÷ 40%, and concrete up to 20%.

Experiments have established that it is expedient to manufacture flexible columns with prestressing reinforcement of classes A-IV (A600), A-V (A800). Prestressing increases the rigidity and crack resistance of columns and improves the conditions for transporting long columns. In addition, it allows to reduce transverse reinforcement and mechanize reinforcement work. Therefore, compared with columns made of ordinary reinforced concrete, the consumption of steel in such columns is reduced by up to 40%.

Longitudinal reinforcement in sections of solid structures can be placed symmetrically when M 1 ≈ M 2 or the ratio of a larger moment to a smaller one is not more than 20%; asymmetrically - when M 1 >> M 2. Rational reinforcement in most cases is symmetrical reinforcement.

The distance between the axes of the longitudinal rods installed along the sides of the column cross section should not exceed 400 mm. If, according to the calculation, longitudinal reinforcement is not required on the larger side of the column section, then in this case it is necessary to install structural rods with a diameter of 12 mm so that the distance between the longitudinal rods of this side does not exceed 400 mm.

It is recommended to install the smallest possible number of longitudinal rods in the cross section of the column by increasing their diameter. The recommended and minimum allowable number of longitudinal rods for installation in the cross section of the column is given in Table. 4.1.

Table 4.1.

If the height of the section does not exceed 500 mm and this side has no more than four rods, then it is allowed not to install transverse rods or studs.


Rice. 4.7. Reinforcement of columns with welded frames

1 - flat welded frames; 2 - connecting rods (studs); 3 - flat welded reinforcing mesh; 4 - longitudinal rods

The step of the transverse rods should be no more than 500 mm and no more than the values ​​\u200b\u200bspecified in Table. 4.2.